On May 19th, the machines were installed. Six machines were hauled back from South Fourth Ring Road using a flat-nosed truck hired from the logistics park. The driver surnamed Zhao waited for two hours until the last machine was lifted down. He rolled up the cardboard on the truck bed into a tube, shoved it into the cab, and said the cardboard could still be used. The machines were lifted down one by one, with four people per machine. Li Lei supported from underneath while Zhao Peng received from above. After receiving one, he patted the machine with his hand and said, "This one is stable."

On the day the machines were hauled back, the foreman surnamed Fu blocked the workshop entrance with one foot stepping on the threshold, saying that the ground wasn't thoroughly dry, and if they installed them today, the machines would tilt after three months.

"The ground was poured on the 14th with No. 400 cement, five days ago." Zhao Peng put down the tape measure in his hand.

"It's dry, but it hasn't cured long enough." The man surnamed Fu scraped the ground with his toe. "If it hasn't cured enough and you press heavy things on it, the soil underneath will sink. Sink it by half a millimeter, and the machine will tilt."

"Sink by half a millimeter, how do you know?"

"I've done it once before." He pulled his foot back. "That time it was the factory's old line. Six machines were installed for half a year, and two of them tilted. We had to dismantle and reinstall them, which took a month."

Engineer Qin listened from the side. Hearing this, he squatted down, pressed his hand against the ground, and looked up after pressing. "Add shim irons and make them a bit thicker."

To push the machines into the workshop, they used a pallet jack. The pallet jack was borrowed by Li Lei from the logistics park for eighty per day. Its hydraulics leaked a bit, making it slow to pump—every pump only raised it half an inch.

Installing the machines wasn't just about pushing them in; they also had to be aligned. A level was placed on the tabletop, measured once horizontally and once vertically. Both directions had to be level. If it was level horizontally but not vertically, the machine would shake when running. Once it shook, the placement head would deviate; deviate by a silk, and the pin would be placed crookedly.

When installing the first machine, the air bubble leaned to the left. Zhao Peng used shim irons, adding one piece and checking once, until the seventh piece when the bubble reached the middle.

"Seven pieces."

"Seven pieces, that's too many."

"Even if it's too many, it's better than being uneven." He took down the level and wiped the bottom with his sleeve. "If it's uneven, the placed components will be deep on one side and shallow on the other. On the deep side, the solder will be squeezed out; on the shallow side, it won't solder properly."

Engineer Qin watched from the side. Seeing the seventh piece, he pulled his hand out of his sleeve, pressed it against the shim irons, didn't speak, and tucked his hands back in.

The anchor bolts were tightened to seventy percent. The remaining thirty percent would be tightened after the machines warmed up from running, because machines expand when hot. Expanding even a little bit meant the bolts needed to be loosened accordingly. If tightened completely to death, the machine would warp.

When installing the third machine, the pallet jack's hydraulics leaked severely—it took three pumps to rise an inch. Li Lei squatted down to look, stared for a long time, pulled a roll of thread seal tape out of his pocket, wrapped it around twice, pumped it a couple of times, and it rose.

"Can it hold until the installation is finished?"

"Can't hold." He stuffed the thread seal tape back into his pocket. "It holds one machine at a time. The last three machines, we carry."

The last three machines were carried in. Four people, each machine weighing over three hundred catties, carried them into the workshop. The carriers were drenched in sweat, and sweat dripped onto the concrete floor, forming little round dots. When the dots dried, they left a ring of white marks.

On May 20th, the machine installation was completed. Temporary power was connected for a dry run.

A dry run meant running the program without placing boards, letting the machine go through its routine by itself, and seeing if it stopped accurately afterwards. The first machine ran a dry run three times, and all three times it stopped at the exact same position. Zhao Peng measured it with a caliper, and the margin of error was half a silk.

"Half a silk, that works."

"Half a silk is just a dry run," Engineer Qin said. "Once you put boards in, it won't be half a silk anymore."

On May 21st, the first test run took place.

The temporary power could only support two machines—one placement machine and one reflow soldering machine. They placed during the day and soldered at night, so for the first run, only one machine was turned on to run a hundred boards.

One hundred boards, from printing to placement, from placement to reflow, and from reflow to inspection, took two hours.

Printing was the first step: solder paste was printed onto the pads, and after printing, a magnifying glass was used to check for accumulations or shortages. Placement was the second step: the nozzle picked up a component from the material tape, turned, and placed it down, pressing slightly during placement. If pressed too hard, the solder paste would be squeezed out; if pressed too lightly, the pins would dangle. Reflow was the third step: the boards passed through the oven. Once passed through, the solder melted and then solidified. As it solidified, the pins were soldered on.

Inspection was the final step. Sister Liu and the other two took one board each, checked with a magnifying glass, and sorted them into good, usable, and defective.

After inspection, sixty-three pieces were good.

Zhao Peng wrote the number on the blackboard. After writing, he took a step back to look, then weighed the chalk in his hand. "Sixty-three."

"Sixty-three, what kind of number is that?"

"Out of one hundred boards, sixty-three came out—sixty-three percent." He put down the chalk. "That furnace at Cuis yields ninety-seven point four percent."

"How much is the difference?"

"A difference of thirty-four points." He tapped on the sixty-three on the blackboard. "Thirty-four points means three hundred and forty pieces fewer a day, and ten thousand fewer a month."

"Ten thousand fewer a month means ten thousand pieces will take two months." Sun Qian calculated from below. "For those ten thousand pieces on July 10th, relying on the new line, it'll be too late."

"It will be in time," Engineer Qin said. "Sixty-three today, sixty-four tomorrow, adding one point a day. In thirty-four days, it will be ninety-seven percent."

"Adding one point a day, can we add it?"

"If we can't add it, we find the problem." He patted the machine with his hand. "Finding one point a day, thirty-four points in thirty-four days. If I can't find them, I'll leave."

The second run: one hundred boards, sixty-four.

"One more piece."

"One more piece is still more." Zhao Peng wrote sixty-four below sixty-three. After writing, he wiped the blackboard with his hand. "We'll crawl up piece by piece."

Half a silk.

In the afternoon, Zhao Peng dismantled the feeders of all six machines one by one. After dismantling each one, he measured it with a dial indicator and wrote down the measurement on a piece of paper.

The feeders were the tongue of the machine. The material tape passed through them; as one passed, it was cut. The cutting relied on a free clearance. The clearance for a new machine was two silks, while one that had run for a year was three and a half silks. When the clearance became too large, the material tape would deviate. If it deviated even a bit, the nozzle would suck air in vain. Every time it sucked air in vain, one piece was lost.

He wrote six numbers on the paper, and after finishing, pushed the paper over.

One, 2.0; Two, 2.1; Three, 2.5; Four, 2.1; Five, 2.2; Six, 2.3.

"The third machine, 2.5."

"2.5, how much more is that?"

"Half a silk more." He put away the dial indicator and packed it back into the box. The box was plastic with one broken clasp. "Half a silk more will cause it to suck air in vain. Every time it sucks air in vain, you lose one piece. Out of three thousand pieces a day, you lose thirty pieces."

"What about the others?"

Zhao Peng didn't speak. He pushed the paper over. Looking at the six numbers on the paper, he tapped his finger on 2.5, then tapped around it.

"All six machines have been tampered with."

"Tampered with?"

"A new machine has two silks. Among these six machines, the lowest is already 2.0, which is the number for a machine that has run for a year." He snapped the box shut. "The feeders on all six of these machines have been replaced, and the replacements aren't new ones—they're ones that have been run for a year."

The workshop fell silent for a moment, so quiet that you could hear the fan from the reflow soldering side. The fan was spinning unevenly—fast for one circle, slow for the next.

Sister Liu put down the board in her hand. She placed it down very gently, and the board landed on the cloth without a sound.

Engineer Qin stood to the side without speaking. After a good while, he pressed his hand against the machine, took his hand back after pressing, and his fingers were stained with a bit of oil.

"This line can run."

"All six machines have been tampered with, and it can still run?"

"As long as it can move, it can run." He wiped his hands on his pants. "I'll vouch for the components produced, and if they can't be run, I'll dismantle it."

Zhao Peng folded the paper twice, stuffed it into his jacket pocket, and patted his pocket after stuffing it in. "All six machines were tampered with; that family took the good ones away and installed old ones."

Sister Liu asked for the paper, copied it once into the sorting record book, and after copying, pasted it next to the machine. She stepped back to look after pasting it, and said, "Look at these six numbers once a day and see which way they go."

"Even if they're old, they're original factory old," Engineer Qin said. "Original factory old is more accurate than new ones bought outside."

"Does the person selling the machines know?"

"The seller knew it in their heart, which is why they were willing to drop the price from 130,000 to 126,400." Engineer Qin walked toward the outside of the workshop. When he reached the door, he patted the door frame with his hand, causing a bit of dust to fall from it.

Actually, I wasn't surprised that the first run produced sixty-three; because the machines were old, this number was considered normal; but normal wasn't enough either; however, whether it's enough depends on what comes later; and there are still five more runs ahead; later, Zhao Peng measured the clearances all over; anyway, none of the six machines were uniform; therefore, I copied the six numbers onto a piece of paper; after copying, I raised my hand and pasted the paper to the wall.

Just pasting the six numbers up didn't mean the machines were fixed; so I had it run another time; and this time, the run was on the night shift.

It was just that running this night shift brought out even more issues; because the lights were dim and hands were slower; so the numbers were lower than during the day; but being low also had its advantages; and only when it's low do you know where the gap lies; later, Zhao Peng copied the numbers onto the wall; anyway, once copied up, it couldn't be wiped away; therefore, I had him paste the six numbers separately.

Zhao Peng took that piece of paper back and copied it again—six numbers, one right after another. After copying, he pasted it on the wall next to the machine, pressed his hand against the paper, and said, "All six machines, dismantle them entirely."